Wattplate

Amp Hours to Watt Hours Calculator

Ah to Wh, battery runtime and battery bank size.

Mode
Convert

Rated output

Estimate

Energy

1,200Wh

100 Ah at 12 V holds 1,200 Wh (1.20 kWh).

Amp-hours100 Ah
Volts12 V
Kilowatt-hours1.20 kWh

Working

  1. Watt-hours = amp-hours × volts = 100 Ah × 12 V = 1,200 Wh
  2. Kilowatt-hours = watt-hours ÷ 1,000 = 1,200 Wh ÷ 1,000 = 1.20 kWh

Model PL-04

The lamp compares the load with the UPS watts you type, or with one home battery's continuous output from its datasheet; it stays off otherwise. Estimate; your equipment's manual wins.

Quick answer

A 200 Ah 12 V LiFePO4 battery holds 2,400 Wh. At 80% usable and 90% efficiency it delivers 1,728 Wh, so a 500 W load runs for about 3 h 27 min.

Rule of thumbWatt-hours = amp-hours × volts: 100 Ah at 12 V is 1,200 Wh; at 48 V the same 100 Ah is 4,800 Wh.

NoteEstimate from physics and maker data. Read the labels; your equipment's manual wins. This is an estimate from physics and maker data, not engineering or code advice. Hire a licensed electrician for the work.

Watt-hours (Wh) by amp-hours and volts
Battery12 V24 V48 V
50 Ah6001,2002,400
100 Ah1,2002,4004,800
200 Ah2,4004,8009,600
300 Ah3,6007,20014,400
Runtime in hours of a 100 Ah 12 V battery at 90% efficiency
LoadLiFePO4 80%Lead-acid 50%
100 W8.65.4
300 W2.81.8
500 W1.71.0
1,000 W0.80.5

Runtime is rounded down. Your battery's label and your load's real draw decide the real figure.

How to convert amp hours to watt hours

Amp hours (Ah) say how much charge a battery holds. Watt hours (Wh) say how much energy it holds. A battery label that prints only amp hours leaves out the voltage, and the voltage is what turns charge into energy:

  • Watt hours = amp hours × volts
  • Amp hours = watt hours ÷ volts

A 100 Ah battery at 12 V holds 1,200 Wh. The same 100 Ah in a 48 V bank holds 4,800 Wh, four times as much, because every amp hour is pushed at four times the voltage. Divide watt hours by 1,000 for kilowatt hours (kWh), the unit on an electric bill.

Use the Convert mode when you only want the unit change. The tool prints the step with your numbers in it, so you can check it by hand.

Why a 12 V lithium battery can be 12.8 V

LiFePO4 cells have a nominal voltage of 3.2 V, and four of them in series make 12.8 V. That is why a “12 V 100 Ah” lithium battery is often listed at 1,280 Wh and not 1,200 Wh. The 12.8 V, 25.6 V and 51.2 V chips in the tool fill the volts box with those nominal figures. Use the voltage your battery label prints; the difference between the two is about 7%.

How long will a battery run a load

The Runtime mode answers the question “how long will my battery last?” in four steps:

  1. Battery energy: amp hours × volts.
  2. Usable energy: battery energy × the share you may use (depth of discharge).
  3. Delivered energy: usable energy × the efficiency of the inverter, or 100% for a DC load.
  4. Runtime: delivered energy ÷ the load in watts, plus the inverter’s idle draw if you know it.

Pick the battery type to set the usable share. Lead-acid is usually sized to half its rating, LiFePO4 to 80% as a planning figure, and some lithium makers rate 100%. A portable power station is one switch: it sets 100% usable and 85% efficiency overall, which is the factor power-station makers use.

The runtime is rounded down, so the tool never promises more than the arithmetic gives. The idle watts box is the inverter’s own no-load draw from its spec sheet. An inverter that sits switched on all night uses energy even with nothing plugged in, and rivals that skip this field overstate the runtime.

A note on lead-acid and high draw

A lead-acid battery gives less than its rating when you pull the current out fast. The ratings are usually measured over 20 hours, so a draw above the capacity divided by 20 shows the caution line. The tool does not guess how much capacity you lose, because the loss depends on the battery. Treat the runtime for a heavy load on lead-acid as the best case. Lithium batteries are affected far less.

UPS and home battery backup

The Backup unit box at the top of Runtime mode fills the other boxes from a spec sheet, and you can still type over any of them. UPS fills one 1500 VA unit: 1,000 W with two 12 V 9 Ah sealed lead-acid batteries in series (CyberPower CP1500PFCLCD). Use the watts on your label, not the VA. The UPS answer is in minutes and runs high at heavy load, so the maker’s runtime chart wins.

Tesla Powerwall 3 and FranklinWH aPower 2 rate usable energy in kWh at the AC side, so the tool sets 100% usable and 100% efficiency and multiplies by the units. The lamp checks your load against the UPS watts or one home battery’s continuous output. For a Powerwall 2 or another battery, leave the box on Any battery and type its usable kWh.

How big a battery bank do I need

The Bank mode starts from the energy you use in a day:

  1. Bank energy: daily watt hours ÷ inverter efficiency × days between charges ÷ the usable share.
  2. Bank amp hours: bank energy ÷ system volts.
  3. In series: system volts ÷ one battery’s volts, rounded up.
  4. In parallel: bank amp hours ÷ one battery’s amp hours, rounded up.
  5. Batteries: in series × in parallel.

Batteries always round up, because a bank that is a little too small runs flat early. Series connections add voltage and keep the amp hours of one battery. Parallel connections add amp hours and keep the voltage. A 48 V bank of 12 V 200 Ah batteries needs four in series, and a 600 Ah target takes three of those strings, 12 batteries in all.

Going to a higher system voltage can change the count, because the series and parallel steps round separately. Try 12 V and 24 V and compare. When the parallel count is high, the tool reminds you to check the maker’s limit on parallel batteries.

Worked example

  1. Inputs: 200 Ah at 12 V, LiFePO4 (80% usable), 90% efficient, 500 W load.
  2. Battery energy = amp-hours × volts = 200 Ah × 12 V = 2,400 Wh
  3. Usable energy = battery energy × depth of discharge = 2,400 Wh × 0.8 = 1,920 Wh
  4. Delivered energy = usable energy × efficiency = 1,920 Wh × 0.9 = 1,728 Wh
  5. Runtime = delivered energy ÷ load = 1,728 Wh ÷ 500 W = 3.4 h, rounded down (3 h 27 min)
  6. Battery draw = load ÷ (efficiency × volts) = 500 W ÷ (0.9 × 12 V) = 46.3 A

Questions people ask

How do I convert amp hours to watt hours?

Multiply the amp hours by the battery voltage. A 100 Ah battery at 12 V holds 100 × 12 = 1,200 Wh, and the same 100 Ah at 48 V holds 4,800 Wh. To go the other way, divide the watt hours by the volts: 2,400 Wh at 12 V is 200 Ah.

How long will a battery run my load?

Multiply the battery watt hours by the share you can use and by the inverter efficiency, then divide by the load in watts. A 12 V 200 Ah LiFePO4 battery at 80% usable and 90% efficiency runs a 500 W load for about 3.4 hours (3 h 27 min). The tool rounds the runtime down, never up.

How much of the battery can I use?

Makers and sellers size lead-acid batteries to 50% of their rating. For LiFePO4 the planning figure is 80%, and some makers rate their lithium batteries for 100%. Use the figure from your battery maker, and pick the custom box if it differs.

How big a battery bank do I need for a day or more of use?

Divide the daily watt hours by the inverter efficiency, multiply by the days you want between charges, divide by the usable share, then divide by the system volts to get amp hours. Divide that by one battery to get how many go in parallel, and round up. The system volts divided by one battery voltage gives how many go in series.

How long will a UPS last?

Check that the load fits first: use the watts on the label, not the VA. A 1500 VA UPS can be 900 W (APC BR1500MS2) or 1,000 W (CyberPower CP1500PFCLCD). Pick UPS in Runtime mode for an estimate, then check the maker's chart: CyberPower lists 10 minutes at half load and 2.5 minutes at full load for that unit.

How long will a Powerwall run my house?

Divide the usable energy by your load. A Powerwall 3 holds 13.5 kWh AC, so a steady 1 kW load runs about 13.5 hours (Freedom Solar, EnergySage), and it delivers up to 11.5 kW at once. A Powerwall 2 also lists 13.5 kWh but only 5 kW continuous.

Related guides

Sources

Data last verified: Page updated

Written and checked by Ali, who is not a licensed electrician.

Before you wire anything

These calculators give estimates worked out from physics and published maker data. They are not engineering, design or code advice, and they do not replace an inspection.

Electrical codes differ by edition and by town. Your local inspector, the authority having jurisdiction (AHJ), has the final say on wire size, conduit, boxes and breakers.

Mains wiring can kill and can start fires. Unless you are trained for it, hire a licensed electrician, and get a permit where your town requires one.