Wattplate

Transformer Size Calculator

Transformer calculator: the next standard kVA size, with amps on both sides.

By Ali (not a licensed electrician) Updated

Phase
Load in

Use the nameplate figure. ABB and Rex work their kW examples at 0.80.

Line to line: 208 for 208Y/120, 480 for 480Y/277.

Room for growth, a design choice, not a code number. A 25% margin loads the unit to 80%.

Rated output

Rated load

Standard size

75kVA

Pick a 75 kVA three-phase transformer: 50.00 kVA of load plus 20% is 60.00 kVA.

Load50.00 kVA
With 20% margin60.00 kVA
Load on the rating66.7%
Secondary full-load, 208 V208.2 A
Primary full-load, 480 V90.2 A
  • One size down, 45 kVA, is below the 60.00 kVA needed.
  • Each side has its own full-load amps, 208.2 A at 208 V and 90.2 A at 480 V here: the primary and secondary breakers or fuses and wire follow NEC 450.3 and Article 240, so each side is sized on its own.
  • Installing or servicing a transformer is a job for a qualified electrician: Square D and Eaton both say to turn off and lock out power first, because shock and arc flash can kill.

Working

  1. Load: 40 kW ÷ 0.80 = 50.00 kVA (138.8 A at 208 V)
  2. With margin: 50.00 kVA × 1.20 = 60.00 kVA
  3. Standard size: the next three-phase rating at or above 60.00 kVA is 75 kVA; the load is 66.7% of it
  4. Secondary: 75,000 ÷ (1.732 × 208 V) = 208.2 A
  5. Primary: 75,000 ÷ (1.732 × 480 V) = 90.2 A

Model PL-07

The margin is a design choice, not a code number (ABB, Consulting-Specifying Engineer). The 125% continuous-load rule sizes breakers and wire, not the transformer.

Quick answer

A 40 kW load at power factor 0.80 on a 208Y/120 V three-phase secondary is 50 kVA; with a 20% design margin, the next standard size is 75 kVA.

Rule of thumbTypical: add your margin to the load in kVA, then round up; common three-phase sizes are 15, 30, 45, 75, 112.5, 150, 225, 300, 500, 750 and 1,000 kVA.

NoteTypical sizing from maker data. Primary and secondary protection and wire follow NEC 450.3 and Article 240: check your code edition and your local inspector (AHJ). This is an estimate from physics and maker data, not engineering or code advice. Hire a licensed electrician for the work.

Standard kVA sizes: single-phase and three-phase

Standard dry-type transformer sizes in kVA: the steps this calculator rounds up to
TypeSizes in kVA
Single-phase1, 1.5, 2, 3, 5, 7.5, 10, 15, 25, 37.5, 50, 75, 100, 167, 250, 333
Three-phase3, 6, 9, 15, 30, 45, 75, 112.5, 150, 225, 300, 500, 750, 1,000

Transformer sizing chart: three-phase full-load amps by kVA

Full-load amps per line of three-phase transformers, by kVA and line-to-line voltage (kVA × 1,000 ÷ (1.732 × volts))
Rating208 V240 V480 V
15 kVA41.636.118.0
30 kVA83.372.236.1
45 kVA124.9108.354.1
75 kVA208.2180.490.2
112.5 kVA312.3270.6135.3
150 kVA416.4360.8180.4
225 kVA624.5541.3270.6
300 kVA832.7721.7360.8
500 kVA1,387.91,202.8601.4

Single-phase transformer full-load amps by kVA

Full-load amps of single-phase transformers, by kVA and voltage (kVA × 1,000 ÷ volts)
Rating120 V240 V480 V
15 kVA125.062.531.3
25 kVA208.3104.252.1
37.5 kVA312.5156.378.1
50 kVA416.7208.3104.2
75 kVA625.0312.5156.3
100 kVA833.3416.7208.3
167 kVA1,391.7695.8347.9

Computed, not copied: a few cells of makers' printed tables differ by a tenth of an amp.

How to size a transformer in 3 steps

Turn the load into kVA, add your design margin, then take the next standard size up: 40 kW at power factor 0.80 is 50 kVA, 60 kVA with a 20% margin, so a 75 kVA transformer.

Get the kVA from a nameplate or load schedule, from kW ÷ power factor, or from amps: amps × volts ÷ 1,000 on single phase, times 1.732 as well on three phase, using line-to-line volts. Size from the calculated or measured load, not the breaker or panel rating (Consulting-Specifying Engineer, ABB). ABB says never round down. The watts to amps calculator does the kW, amps and kVA conversions alone.

Standard transformer sizes in kVA

Three-phase dry-type transformers come in 3, 6, 9, 15, 30, 45, 75, 112.5, 150, 225, 300, 500, 750 and 1,000 kVA, and single-phase units in 1 to 333 kVA, with 15, 25, 37.5, 50, 75, 100, 167, 250 and 333 the common steps.

Eaton’s design guide lists these steps, and Square D, Rex and the federal efficiency rule (10 CFR 431.196) list the same ones. 50 kVA is a single-phase step only and 112.5 kVA is three-phase only. Not every voltage comes in every size: check the maker’s catalogue (ABB).

Why transformers are rated in kVA, not kW

A transformer’s rating is kVA, the volts times amps it can carry, so a load given in kW is divided by its power factor first: 40 kW at power factor 0.80 is 50 kVA, more than a 45 kVA unit carries. Square D warns that leaving out the power factor undersizes the transformer.

Power factor is 1 for heaters and ovens and about 0.85 for a motor of 10 hp or more at full load, the same two presets as the watts to amps calculator.

Primary and secondary full-load amps

A transformer carries different amps on each side: ABB’s 30 kVA, 600 V to 208Y/120 V example draws 28.9 A on the primary and 83.3 A on the secondary. The primary is the supply side and the secondary the load side.

Full-load amps are kVA × 1,000 ÷ (1.732 × volts) on three phase and kVA × 1,000 ÷ volts on single phase, worked from the size you buy, not from the load. The lower-voltage side always carries more amps. A 120/240 V single-phase secondary is worked at 240 V. The two tables above list the amps of common sizes.

Spare capacity: a design margin, not a code number

A 15 to 25% margin for growth is common, but ABB calls it a design choice, not a code rule, and Consulting-Specifying Engineer adds 20% unless the facility directs otherwise.

Eaton says the nameplate kVA is the continuous rating, built to run 24 hours a day, 365 days a year. Rex warns that chronic overload ages the insulation. Don’t stack a safety margin and a growth allowance (ABB). The 125% continuous-load rule is for breakers and wire, not for the transformer’s kVA: see the breaker size calculator.

Breakers, wire, motors and hot rooms: what to check next

The size is the first step: protection and wire on each side follow NEC 450.3 and Article 240, motors that start often can need more kVA, and above 3,300 ft or in a room hotter than 40 °C a transformer carries less than its nameplate (Eaton, Rex). The wire size calculator sizes the wire for each side.

No transformer alone turns single-phase into three-phase (Eaton, Hammond); a single-phase load can run from two wires of a three-phase supply (Acme). This calculator does not cover buck-boost transformers. Installing or servicing a transformer is a job for a qualified electrician: power off and locked out first, because shock and arc flash can kill (Square D, Eaton).

Worked example

  1. Inputs: 40 kW at power factor 0.80, three phase, 208 V secondary, 480 V primary, 20% design margin.
  2. Load: 40 kW ÷ 0.80 = 50.00 kVA (138.8 A at 208 V)
  3. With margin: 50.00 kVA × 1.20 = 60.00 kVA
  4. Standard size: the next three-phase rating at or above 60.00 kVA is 75 kVA; the load is 66.7% of it
  5. Secondary: 75,000 ÷ (1.732 × 208 V) = 208.2 A
  6. Primary: 75,000 ÷ (1.732 × 480 V) = 90.2 A

Questions people ask

What size transformer do I need for a 225 amp panel at 208Y/120 V?

112.5 kVA if the panel really draws its full 225 A: 225 A at 208 V three phase is 81.06 kVA, just above the 75 kVA step. Consulting-Specifying Engineer and ABB both size from the calculated design load instead of the panel rating, and that often points to a smaller unit.

What size transformer for 100 amps at 240 volts?

37.5 kVA with a 20% margin: 100 A at 240 V single phase is 24 kVA, 28.8 kVA with the margin, and the next single-phase size up is 37.5 kVA. With no margin 25 kVA fits, the size Rex Power Magnetics gives for the same load.

How many amps is a 75 kVA transformer?

90.2 A on a 480 V three-phase primary and 208.2 A on a 208Y/120 V secondary: 75,000 ÷ (1.732 × 480) and 75,000 ÷ (1.732 × 208), the same figures as Eaton's table. Each side is wired and protected for its own amps.

Can I load a transformer to 100% of its kVA?

100% of the nameplate kVA is the continuous rating: Eaton designs its dry-type units to carry it 24 hours a day, 365 days a year. Makers build in no continuous overload, though, so many designers leave 15 to 25% for growth (ABB), and a 25% margin loads the unit to 80%.

Do I need to add 125% when sizing a transformer?

No 125% rule applies to the transformer's kVA: ABB says a growth allowance of 15 to 25% is a design choice, not a universal rule. The 125% people quote is the continuous-load rule for breakers and wire (NEC 210.20(A)), and the transformer's own protection follows NEC 450.3.

Sources

Data last verified: Page updated

Built and checked by Ali, who is not a licensed electrician.

Before you wire anything

These calculators give estimates worked out from physics and published maker data. They are not engineering, design or code advice, and they do not replace an inspection.

Electrical codes differ by edition and by town. Your local inspector, the authority having jurisdiction (AHJ), has the final say on wire size, conduit, boxes and breakers.

Mains wiring can kill and can start fires. Unless you are trained for it, hire a licensed electrician, and get a permit where your town requires one.